Roof, siding, windows, gutters and paint: what order to do exterior projects

The order is not a matter of taste. Each part of the exterior laps over or tucks under the next, so doing them out of sequence means tearing into new work to fix a connection. Here is the usual order, the reasons behind it, and how to split it across several seasons.

Planning6 min readReviewed 2026-09-17

The short version

  • Work from the top down and from the wall outward: roof, then windows and doors, then siding and trim, then gutters, then paint.
  • The roof goes first because its flashing at walls and chimneys tucks behind the siding. Siding first means disturbing new siding later.
  • Windows go in before or with the siding so their flashing laps correctly into the water-resistive barrier.
  • Gutters go up after the roof edge and fascia are finished. Paint goes on after all carpentry repairs, and after the other trades have left.
  • If you phase the work over several years, fix water problems first and make sure each phase leaves the next one a clean connection.

The usual order, and the logic behind it

A house exterior is a set of layers that shed water downhill. University of Minnesota Extension's rule for a drainage plane is that every layer must lap out and over the layer below it. That one rule sets most of the sequence: the parts that sit higher, or that tuck behind other parts, go in first.

  • 1. Roof. Highest layer; its flashing at walls, chimneys and dormers tucks behind the siding.
  • 2. Windows and doors. Their flashing has to be integrated with the water-resistive barrier before siding covers it.
  • 3. Siding, trim, soffit and fascia. Laps over the window flanges and the roof's step flashing, and leaves the required clearances at roof lines.
  • 4. Gutters and downspouts. Hang on finished fascia, under a finished roof edge.
  • 5. Paint. Last, over repaired and primed wood, after ladders and other trades are done.

Why the roof comes before the siding

Where a roof meets a wall — a dormer, a second-story wall above a porch, a garage roof against the house — the roof is flashed with step flashing that runs up the wall behind the siding. Wisconsin's Uniform Dwelling Code requires flashing at wall and roof intersections, and it requires the end of the roof flashing at an eave that meets a sidewall to divert water away from the wall and onto the roof or into the gutter. That piece is usually called kickout flashing. Chimneys must be flashed and counter-flashed.

Siding manufacturers build their instructions around those details. James Hardie's best-practice guide calls for 2 in. of clearance where siding meets a roof and for kickout flashing at roof-to-wall ends. LP SmartSide's instructions call for 1 in. of clearance from roofing, step flashing with an upper leg of at least 4 in., and kickout flashing.

If the siding goes on first and the roof is replaced a year later, the roofer has two poor choices: reuse old step flashing, or cut and remove new siding to replace it. Doing the roof first lets the siding crew finish over new flashing with the right clearances. Roof work is also hard on walls — tear-off debris, ladders and foot traffic mark new siding and new paint.

Windows before, or with, the siding

A new-construction window with a nailing flange is flashed into the wall: the water-resistive barrier and flashing tapes lap so that water running down the wall is carried out over the window head and past the sill. The UDC requires flashing at the tops of doors and windows. University of Minnesota Extension adds a detail that matters: don't caulk the bottom flange of a window, because that traps water that needs to drain out.

That lapping only works if the window goes in before the siding covers the barrier. Replacing flanged windows after new siding means cutting back siding and trim, and patching the barrier around each opening. If both projects are coming, do windows and doors first or with the siding.

Insert replacement windows, which fit inside the existing frame and leave the exterior trim in place, are less tied to the siding schedule. Even then, trim that will be wrapped or replaced with the siding is best finished once, after the windows are in.

In a home built before 1978, any paid window replacement falls under Wisconsin's lead-safe renovation rule, even when the old windows are vinyl. See lead-safe renovation in Wisconsin.

Gutters after the roof edge and trim

Gutters hang on the fascia, below the drip edge at the roof's lower edge. The drip edge goes on with the roof, and fascia repairs or wraps usually happen with the siding and trim. Hanging new gutters before either is finished means taking them down again.

The siding details point the same way. James Hardie and LP both call for a 1 in. gap between the end of a gutter and the siding, and the kickout flashing the UDC calls for is there to direct water into the gutter rather than down the wall. Those pieces fit together best when the roof edge and wall are already finished.

Downspouts finish the job. University of Minnesota Extension recommends discharging them at least 4 ft from the foundation. New gutters are the last step of water management, not the first.

Paint last, after the carpentry

Paint is the finish on everything else, so it goes on after rotted trim and siding boards are replaced, after joints are caulked, and after the roofers, window installers and gutter crew are done leaning ladders on the walls.

Two product rules affect the timing. Sherwin-Williams' Duration Exterior data sheet says standard latex primers cannot be used below 50°F, so new or bare wood needs a warm enough window to be primed. And primed fiber cement and engineered wood have a clock: James Hardie's instructions require painting within 180 days, and LP's say as soon as possible or within 180 days. A fall siding job on primed product can be painted the following spring, but not left for years.

If new siding is factory-finished, the paint phase may shrink to trim, doors and any wood that stays. See when you can paint an exterior here for the weather side of the schedule, and exterior painting for what the work includes.

Where interior work fits

Fix the source of water before fixing what it damaged. A ceiling stained by a roof leak or an ice dam should wait until the roof and attic are fixed and the materials have dried; then drywall repair and interior painting can be done once. The same goes for interior trim and paint around new windows — install the windows first.

Phasing over several seasons

Few households do everything in one year. When the work has to be split, rank it by water risk, then plan each phase so it leaves a clean connection for the next.

  • Leaking or failing roof: do it first, whatever else is planned. Talk with the roofer about replacing step flashing and adding kickout flashing at walls now, even if that means removing and resetting a course or two of the old siding.
  • Windows and siding together where the budget allows, so window flashing is integrated with the new barrier once.
  • Gutters with or right after the siding and fascia work.
  • Paint when the carpentry is finished and the weather cooperates — or first, on its own, if the siding is sound and staying.

Seasons shape the phases. Roofing can go on in the cold, but Owens Corning requires hand-sealing shingles around the roof perimeter at or below 40°F. Vinyl siding can go up in the cold with a wider gap — the vinyl industry manual calls for 3/8 in. at openings below 40°F. Painting has the narrowest window. Each phase may need its own permit: Muskego, for example, requires permits for re-roofing and re-siding; see permits in southeast Wisconsin.

One contractor or several

Separate specialists can each be excellent at their trade. The risk is at the connections — step flashing behind siding, window flashing into the barrier, gutter ends at the wall — where each trade can reasonably assume the other one owns the detail. One firm handling several trades has fewer handoffs, but should still be able to explain every connection.

Either way, ask each contractor who is responsible for the flashing at the transitions, and get that in the written scope. C&L Property Improvements does roofing, windows and doors, siding, gutters and exterior painting, provides free estimates, and puts the sequence and the scope in writing.

Questions

Should I replace windows or siding first?

Windows, or both together. Flanged windows are flashed into the water-resistive barrier before siding covers it; replacing them after new siding means cutting into it. Insert replacements that leave the exterior trim alone are less tied to the siding schedule.

Can I paint now and replace the roof later?

Yes, if the siding is sound and staying. Expect some touch-up where the roofers work at walls and chimneys. If the siding is going to be replaced soon, don't paint it first.

Should gutters be replaced with a new roof?

Often it makes sense to do them right after, because the drip edge and fascia are being finished. At a minimum, gutters removed for roofing should be rehung with correct pitch and sealed ends.

What is kickout flashing and why does it matter?

It is the piece at the bottom of a roof-to-wall intersection that turns water out into the gutter instead of down the wall. Wisconsin's code requires the roof flashing there to divert water away from the wall. Without it, water runs behind the siding.

White clapboard farmhouse at dusk with lit windows and a glowing front porch under a red metal awning

Free estimates · Mon–Fri 8 a.m.–6 p.m. · Sat 9 a.m.–6 p.m.

Tell us about the house.

What needs doing, roughly how old the house is, and when you would like it done. C&L will set up a time to look at it in person.